  1. 2016

    • Preliminary design concept and technical studies
  2. April 2017

    • Consultation with local residents on proposed new road
    • State Government consideration of application for a new road
  3. June 2017

    • Community consultation on the proposed residential development
    • Submission of Breakwater Robina development application to City of Gold Coast Council
  4. April-June 2018

    • Public notification (1) of Breakwater Robina development application (Statutory process)
  5. June 2018

    • Meeting with the community to discuss submissions
  6. Mid - Late 2018

    • Public Notification (2) of Breakwater Robina Development application (Statutory process)
  7. 2019

    • We worked closely with the Council throughout 2019 to ensure our vision for a new community is developed through a local and collaborative planning approach
  8. February 2020

    • We lodged an amendment to our application reducing the number of homes to 1,500 and eliminating all podium style development

  9. March-June 2020


    • Council to assess and decide the application
  10. Early 2021

    • Commence construction, subject to approval